Project Description
Client:
ARIET
Project Value:
S$124 million
Project Design:
CPG Consultants Pte Ltd
Contractor:
Kienta Engineering Construction Pte Ltd
WTP provided full Quantity Surveying services for Singtel Data Centre in 2007.
The built-to-suit Green Mark [Gold] Data Centre was completed in 2010 has an overall GFA of 33,785m2 and comprises:
- Tier 4 TIA 942 Standard for DC facilities
- 2000W/m2 of electrical power for DC space
- 22 +/- 1°C DB and relative humidity of 50+/-5% RH
- Chilled water system designated with N + 1 water cooled capacity plus 100% air cooled capacity
- Supply air through raised floor space as an air plenum via supply air grilles
- BMS provided for automatic control and monitoring of plant and equipment