Project Description

Client:

ARIET

Project Value:

S$124 million

Project Design:

CPG Consultants Pte Ltd

Contractor:

Kienta Engineering Construction Pte Ltd

WTP provided full Quantity Surveying services for Singtel Data Centre in 2007.

The built-to-suit Green Mark [Gold] Data Centre was completed in 2010 has an overall GFA of 33,785m2 and comprises:

  • Tier 4 TIA 942 Standard for DC facilities
  • 2000W/m2 of electrical power for DC space
  • 22 +/- 1°C DB and relative humidity of 50+/-5% RH
  • Chilled water system designated with N + 1 water cooled capacity plus 100% air cooled capacity
  • Supply air through raised floor space as an air plenum via supply air grilles
  • BMS provided for automatic control and monitoring of plant and equipment