Project Description
Client:
Land Transport Authority
Project Value:
S$350M
Project Design:
TY Lin International Pte Ltd
WTP was part of the Multi-disciplinary team which provided mainly pre-contract services for this project in 2003.
Completed in 2009, this depot houses the trains for the Circle and Downtown MRT lines.
With a GFA of 100,000m2, this underground depot comprises:
- A depth of 24m at some points
- A capacity for 77 trains
- An administration building with offices, a warehouse, a canteen and a 66KV sub-station above it
This depot located along Upper Paya Lebar Road provides stabling of the trains, maintenance and operational control of the line.